On 7th Decem­ber 2021, the prog­ram admi­ni­stra­tor app­ro­ved the third inte­rim report on the PSP 3 pro­ject.

The veri­fi­ca­ti­on found that no furt­her inte­rim pay­ment was due.

The app­ro­ved sett­le­ment amount of the total eli­gib­le costs in PSP 3 is 13641,44 EUR, the app­ro­ved sett­le­ment amount of the pro­ject grant is 12277,30 EUR.